Excerpt of Sample Budget:  Home Building and House Remodeling Guide

Here is just a excerpt of my Sample Budget that you will receive when you order the Home Construction and Building Guide...



SAMPLE BUDGET WITH ASSUMPTIONS



· PROTECT AND TREAT TREES $1,500.00
    ASSUMPTION: Fence trees in the construction zone with chain link/trim and deep root fertilize
· CONSTRUCTION FENCE $1,500.00
    ASSUMPTION: Chain link fence site per City code.
· SITEWORK $4,500.00
    ASSUMPTION: Excavation and excess soil haul off of site for foundation. Rough grading and backfill after the installation of foundation.
· FOUNDATION $30,180.00
    ASSUMPTION: Installation of approximately 576 linear feet of 12" X 24" concrete beam including three fire place pads; 100 (12") concrete piers - 8 ft deep and 672 square feet of 5" garage concrete floating floor over compacted fill.
    • 576 X 42 = 24,192
    • 100 X 80 = 8,000
    • Pump = 800
    • Pier & Beam: 33,000
    • 672 X 5.75 = 3,864
    • Pump = 800
    • Garage Floors: 4,664
    • Total 37,664
CONCRETE PORCH CAPS $3,967.00
    ASSUMPTION: 828 Square feet of bar/veranda/covered porch/steps. 99 square feet of front porch/steps and 107 square feet of side patio/steps; (Total 150 linear feet of steps and 1,034 square feet of porch cap)
    • 150 X 7.50 = 1125
    • 1034 X 5.75 = 5925
    • Pump 1 X 800 = 800 7850
· BRICK PAVER PORCHES - UNGLAZED $6,163.00
    ASSUMPTION: An allowance of $11.50 square foot (labor and material) for the installation of unglazed brick pavers on the pool storage steps, bar floor, veranda/covered porch/steps, front porch/ steps and side patio/steps.
· INSULATION $6,300.00
    ASSUMPTION: Batt insulate all exterior stud walls, ceilings at attic space, under first and second floor and interior sound batts at designated rooms.
    • R13 Kraft Batts in Exterior walls
    • R30 Kraft Batts in Ceiling
    • R19 underfirst floor and second floor
    • R11 Kraft Batts sound
· GAS LIGHTS $900.00
    ASSUMPTION: $900 Allowance
· DRYWALL $18,888.00
    ASSUMPTION: Install 1/2" sheetrock with a light orange peel texture
    • 5127 X 4.00 = $20,508
· TILE LABOR $10,000.0
    ASSUMPTION:
    • MASTER BATH
    • 111 sf shower/134 sf floor/40 sf shower floor/ceiling
    • 284 sf of marble 12" X 12" tile
    • BATH # 2
    • 160 sf of ceramic tile (100 sf tub/60 sf floor)
    • BATH # 3
    • 160 sf of ceramic tile (100 sf tub/60 sf floor)
    • BATH # 4
    • 190 sf of ceramic tile (110 sf shower/40 sf floor/40sf shower floor/ceiling)
    • LAUNDRY
    • 100 sf floor
    • KITCHEN BACKSPLASH
    • 35 sf
    • 935 sf X 10 = $9,350
    • shower seats/bullnose jambs - $650
    • $10,000


· TILE MATERIAL $5,080.00
    ASSUMPTION:
      • sf of ceramic tile X $4.00 = $2,440
      • 285 sf of marble tile X $8.00 = $2,280
      • 40 sf of backsplash X $8.00 = $360


· METAL FIREPLACE - MASTER
    ASSUMPTION:
      • Majestic 36" metal firebox
      • Gas Logs
      • Marble Surround 30 sf 20 X 30 = 600
· GUTTERS $2,500.00
    ASSUMPTION: Seamless Aluminum
· PAINTING $31,196.00
    ASSUMPTION: Woodwork is painted with oil-base enamel. Drywall areas will be painted with latex. Exterior woodwork will be painted with latex enamel. Two enamel colors and three wall colors. One exterior trim color. Painted brick 5672 X 5.50
· COUNTERTOP - GRANITE $6,220.00
    ASSUMPTION:
      • $60.00 sf allowance
      • Kitchen Granite - 82 sf @ 60 = $4,920
      • Butlers - 10 sf @ $60 = $600
      • Cutouts - 2 X 200 = $400
      • Polished Edge 12 X 25 = $300
      • $6,220
· COUNTERTOP - CULTURED MARBLE $1,400
    ASSUMPTION:
      • Pool Bath - 10 sf X $25 = $250
      • Bath # 2 - 10 sf X $25 = $250
      • Bath # 3 - 10 sf X $25 = $250
      • Bath # 4 - 10 sf X $25 = $250
      • Sink Cut-outs = $400
      • $1,400
· COUNTERTOPS - MASTER BATH - SLAB MARBLE $3,700.00
    ASSUMPTION: Vanities-30 sf X 50 = $1,650
      • Sink Cut-outs = $400
      • Master Tub - 30 sf X $55 = $1,650
      • Tub Cut-out = $200
      • $3,700
· COUNTERTOPS - FORMICA $875.00
    ASSUMPTION: 35 SF x 25 = $875


Copyright © 2003 Bill Manning. All rights reserved.