Excerpt of Construction Checklist - Home Building and House Remodeling Guide

Here is just an excerpt of my Construction Check List that you will receive when you order my Home Construction and Building Guide....

CONSTRUCTION CHECK LIST


___ Install fireplace walls and header

___ Confirm 4" around all openings

___ Check location of all windows, doors and cased openings

___ CHECK FLOOR JOIST FOR NOT INTERFERING WITH TOILET/TUB AND SHOWER DRAINS

___ CHECK FLOOR JOIST FOR NOT INTERFERING WITH CEILING CAN LIGHTS (CENTER OF HALLWAY, STAIRS, ETC.)

___ Drop all tile/marble floors

___ Second floor ceiling height correspond with windows, plate line and roof line

___ Check size of shower door opening(minimum 2' 0" in clear after door installed)

___ Align front door with door/window above

___ Check front door heights

___ Must have solid framing around front door

___ Check window/door fireplace heights

___ Check all openings

___ Check pocket door openings (door placked?)

___ Check doorways

___ Center all windows/doors - exterior elevations and areas above front door, trim walls/toilets

___ Install garage floor drain

___ Confirm Height of Garage Floor

___ Termite treat Garage before plastic

___ Pour garage floor

___ Check all radius and eyebrow framing for accuracy

___ INSTALL INTERIOR DRAIN SYSTEM(PIPING, PLASTIC, GRAVEL, SUMP)

___ Plastic attached to bottom plate

___ Backfill and grade lot to drain

___ Cover void boxes with dirt

___ INSTALL STEEL GIRTERS

___ Clean all trash from site

___ Install sewer trunk line

___ Material drop location

___ Contact electric company representative to complete service survey and E-Wise program

___ (Number of AC Tons, size of project,cooking, heating, hot water and swimming pool power requirements)

___ Order trash dumpster

___ Order temporary construction fence

___ Install Silt Fence

___ ORDER BRICK

___ FRAMER & PLUMBER RECEIVE AC PLAN

___ TERMITE SHIELDS

___ Order floor joist package and hangers

___ Drop decking at all tile/marble areas

___ RUN FLOOR JOIST SYSTEM

___ One square foot of crawl space vent per 150 square foot area

___ Insure girders are staggered on top of piers

___ Block for AC Plenums

___ Check floor joist location not to interfere with AC floor supplies

___ METAL SHIMS

___ INSTALL STRUCTURAL STEEL

___ IS ALL BRICK SUPPORTED

___ CENTER AC FLOOR SUPPLIES UNDER WINDOWS, ETC.

___ Install crawl space access

___ Double floor joist under perpendicular walls

___ PLUMBING ROUGH-IN (WATER, GAS AND SEWER)

___ New sewer line/tap

___ New water line/tap (cut-off within 5' of meter)

___ New gas service line

___ Gas rough-in

___ Check plumbing and gas

___ Check for toilets/shower and tub drains

___ City Plumbing and Gas Rough-in Inspection

___ Confirm AC plan corresponds with furniture layout

___ INSTALL FIRST FLOOR AC DUCTS

___ Insure ducts are clear of crawl space access

___ Seal AC floor supply ducts

___ Install crawl space blower (insulate for noise)

___ Floor joist and AC Duct inspection

___ Install light(s), switch and plug for sump pump in crawl space.

___ Install floor plug and kitchen island electrical

___ Temporary wire sump pump and crawl space blower

___ Install downdraft cooktop vent (need model number for correct size)

___ Order first floor framing package

___ Insulate first floor

___ Install first floor decking

___ TREAT DECKING WITH WATER CEILER

___ After walls popped, check accuracy

___ Install crawl space access

___ Order glass block

___ Order skylights

___ Order front door

___ Check first floor dimensions

___ Check fireplace hearths & area (hearth a minimum of 82")

___ Window rough openings to framer

___ Use microlamb headers on double openings

___ Minimum of 7'6" ceilings under stairways and all rooms

___ Check garage door rough opening/account for concrete garage cap

___ Garage Header - must be engineered

___ ORDER EXTERIOR DOORS a. Which double door operates b. Inswing or outswing c. Three or multiple point locking d. Red oak or white oak e. Light Pattern f. Size of Mutton g. Insulated glass or SP h. Thresholds i. Low E

___ CONFIRM DOOR DROP AND DOOR WIDTH ROUGH OPENING

___ Check fireplace opening for being centered

___ Install Water Heater Platforms (18")

___ Install Mastertub Deck

___ Whirlpool Motor Access

___ Check brick freeze/stucco freeze for accuracy

___ Check nailing of cornice for quality and appearance

___ Is cornish/brick freeze correct in relation to plans

___ PRIME EXTERIOR WOOD

___ FLOOR ATTIC

___ Check for proper roof bracing, collar ties and perlins (Perlins equal to size its bracing)

___ Install roof decking - Kool Ply?

___ Is decking level and confirm use of clips

___ Order cast stone after windows and doors are set

___ Check cast stone depth

___ INSTALL PLUMBING STACKS

___ Plumbing top out

___ Add 6" to copper - air pocket

___ INSTALL FURNACE AND HOT WATER HEATER ROOF VENTS

___ Install metal fireplaces and chimneys (if using straight flue, add second cap due to noise)

___ TAR PAPER AND DRY-IN ROOF

___ DRY-IN ROOF BONNETS WITH TAR PAPER OR PLASTIC

___ Install roofing material

___ CONFIRM FLASHING

___ Do not bend flashing at roof dormers

___ Standing seam roof - layout roof vents/stacks to insure they do not extend through seams

___ If installing a standing seam roof, paint all roof stacks and vents before starting

___ INSTALL ROOF STACK AND VENT BOOTS

___ Install lead roof stack and vent boots

___ Remove toe boards & fill holes

___ Are valleys open or closed

___ Using ridge caps or no ridge caps

___ When installing tile roofs, type of ridges

___ Install attic roof vents, attic power roof vents or turbine vents

___ Install skylights

___ Paint all roof vents and stacks

___ Install Windows

___ COVER WINDOW PANES

___ Shingle clean-up

___ Check for roof leaks

___ CONFIRM WITH MECHANICAL CONTRACTORS NO PIPES, DUCTS OR WIRES IN ATTIC WALKWAYS

___ CONFIRM WITH MECHANICAL CONTRACTORS LOCATION AND SIZE OF HOLES IN CEILING JOIST

___ Confirm all refrigerators and icemakers have water lines and drains

___ Confirm sinks and dishwashers have water lines and drains

___ Pedestal sink plumbing is centered ___ All ceiling can lights are centered and do not interfere with ceiling mold

___ Confirm switch box conduit pipes do not interfere with intercom speakers and volume controls

___ Lay-out backsplash tile - location of plugs

___ Verify location of GFI control plugs (Do not install on exterior or away from zone)

___ Confirm hot water circulating pump

___ Verify powder bath sconce fixture is centered with pedestal sink

___ Verify all wall sconces centered

___ Confirm all boxes, fixtures and cans are secured, centered and in the proper location

___ If Mastertub has a heater, add a circuit

___ Verify lights centered on fireplace

___ Verify breakfast room, entry and dining room fixture lights are centered

___ Verify ceiling fans are centered

___ Verify height of backsplash plugs (center of box. 2" above vanity height - 34" / 38")

___ Verify height of 1/2 wall plugs (39")

___ Install a vent fan for the master bath shower

___ Install a minimum of 3 can light over vanities

___ All wires in return air spaces must be sleeved

___ Confirm extra circuits in attic and under the house (4)

___ Confirm no plugs and switches in mirror

___ Pre-wire for garage door opener infra-reds(add 5' of wire at opener location)

___ Confirm pipe is behind fireplace

___ Rough-in landscape lighting circuits(need one circuit for small lots and two for large lots; need 4 wires per circuit; 1 for security lights, 1 for landscape lights and 2 for switches - front and rear)

___ Verify exterior plugs are correct step-out(brick/stucco)

___ City Electrical Inspection

___ INSTALL BATHROOM EXHAUST VENTS, VENT-A-HOOD ROUGH-IN PIPE, DRYER VENT, UPPER AND LOWER COMBUSTION AIR VENT FOR HOT WATER HEATERS IF APPLICABLE

___ Is vent-a-hood remote and standard

___ Install downdraft cooktop venting(need model # for proper size venting)

___ Confirm ground wires is on HWH cold water pipe, panel box and whirlpool/tubs

___ Cabinet Take-off

___ Verify all cabinets per plans

___ Verify medicine cabinets

___ Verify toe kicks, ceiling mold-top style window molding, corners, type of door,type of material, paint/stain grade,appliance panels, top refrigerator panel, drawers - 1/4" overlay or regular, 2" for UC Fluorescent, Full Extension Guides

___ Confirm left lower family room fireplace matches right lower

___ Have client approve cabinets

___ CONFIRM SINK / APPLIANCES CUT-OUTS

___ ORDER CABINETS

___ Cabinets do not cover fireplace clive

___ Interior trim take-off

___ Check attic stairs for correct operation

___ Confirm attic stairs has insulation panel if in interior

___ INSTALL HARDWOOD FLOOR

___ Do not cover Fireplace Clive

___ Complete stairs before installing Second Floor

___ Confirm with client: a. Grade of wood (quartersawn, select, commons) b. Size c. Pattern d. White oak or Red oak or Pine e. Handscrape

___ If using contemporary base or no shoe mold-install tight against each wall

___ Verify all closets are hardwood on first floor

___ Confirm AC toe kick supplies are cut out correctly

___ Confirm fireplace hearth cut outs

___ Confirm crawl space access cut out is neat and operational

___ Picture frame fireplace hearths and crawl space access(s)

___ Verify expansion spacers

___ Confirm hardwood floor does not interfere with door jambs

___ Check hardwood floor for levelness and imperfections

___ INSTALL CABINETS

___ Cut-out AC toe kick supply vents (2 1/4" x 10 / 2 1/4" x 14)

___ Confirm cabinets are set flush with sub floor - not high

___ Check for complete and straight cabinet installation

___ Verify all cabinets are trimmed with flatmold or scotia mold at walls

___ INSTALL ALL WALL/ CEILING AC SUPPLY AND RETURN GRILLS

___ ORDER INTERIOR TRIM PACKAGE

___ Verify HEIGHT of Interior Doors

___ INSTALL BATHTUB/SHOWER, FIREPLACE, TOP AND FLOOR TILE

___ Float floors to proper height - transition to wood or carpet

___ Lay wood base first so tile will butt against( no shoe mold )

___ Install door jambs after tile is laid

___ Use floorflex instead of thin set

___ Check shower pan for leaks before floating

___ Confirm shower floors have fall in order to drain

___ Confirm shower jamb material - tile, marble or synthetic, soap dish, corner caddy

___ Does shower and backsplash tile have trim pieces? Bull nose or surface cap

___ Client must approve each piece of marble

___ Miter all tile corners & caulk

___ Confirm all shelves have been installed & fit properly

___ Confirm all cabinet doors have been installed & fit properly

___ Construct exterior wood columns

___ Order interior trim pick-up for credit

___ Confirm appliance front on the job